Effingham County Regional Water Supply Facilities 1.5 MG Elevated Water Tank

Description

Effingham County is soliciting the construction of a new 1.5-million-gallon concrete composite elevated water tank as part of the County’s Regional Water Supply Facilities project. The project includes all labor, materials, and equipment necessary to provide a complete and fully operational elevated water storage facility, including the tank foundation, tank erection, site work, piping, painting, electrical systems, instrumentation, SCADA, and related accessories. Major construction components include the elevated tank and foundation, site clearing and grading, gravel access areas, approximately 12-inch PVC water main, flanged piping and control valves, connection to the existing 16-inch water main, fire hydrant assemblies, gate valves, steel casing/jack-and-bore work, chain-link fencing and gates, rip-rap, miscellaneous concrete, erosion and sediment controls, and site restoration. The project also includes a complete electrical, instrumentation, and SCADA system, including electrical service, panels, conduit, wiring, gauges, controls, grounding, lighting, pressure instrumentation, and associated testing and inspections. The electrical plans further identify SCADA equipment, tank lighting, grounding around the tank, service equipment, and provisions for obstruction lighting if required for FAA compliance. Additional work includes tank coating and painting, lettering and logo installation, disinfection and bacteriological testing of the water system, stormwater/NPDES monitoring and reporting, and completion of all regulatory and closeout requirements necessary to place the facility into service. Mobilization Clearing & Grubbing Site Grading Traffic Control 1.5 MG Concrete Composite Elevated Water Tank Gravel Driveway and Areas Inside Fence (See Plans) Flanged Piping and Valves (Includes Non-Freeze Yard Hydrant) Precast Concrete Vault 12" C900 DR 25 PVC Water Main (Includes all Rest. Jt.) 24" Welded Steel Casing (Jack & Bore/Open Trench) Fire Hydrant Assembly 12" Butterfly Valve Connect to Exist. 16" Water Main w/ 16"x12" Tapping Sleeve w/12" GV 7 ft. Site Fencing and Gate Rip-Rap Electrical, Instrumentation and SCADA Misc. Concrete Erosion and Sediment Control Painting, Lettering & Logo for Composite Elevated Water Tank Storm Water Sampling for NPDES Permit Monitoring, NOI, NOT, Record Keeping & Reporting NPDES to GA EPD Alternate Bid No.1 The base bid is for a concrete composite elevated water tank. Bid Alternate No. 1 is for a spheroid elevated water tank and the associated painting, lettering, and logo items. Bidders shall submit prices for both the base bid and the alternate. Subtract Item No. 5 & 19 from the Base Bid and add Item No. 5 & 19 from Alternate Bid No. 1 for new total. 1.5 MG Spheroid Elevated Water Tank Painting, Lettering & Logo for Spheroid Elevated Water Tank Cash Allowances Authorized by Owner & Engineer Cash Allowance (Authorized by Owner & Engineer) Scope of Work SCOPE OF WORK: The purpose of this solicitation is to describe the requirements for: The project includes furnishing all labor, materials, equipment, and services necessary to construct a 1.5-million-gallon concrete composite elevated water storage tank in Effingham County, Georgia. Work includes tank and foundation design and construction, site work, piping, tank erection and painting, electrical systems, supervisory control and data acquisition (SCADA), and related appurtenances, including testing and commissioning, in accordance with the project plans and specifications. GENERAL INFORMATION: Whenever an alteration in the character of the work involves a substantial change in the nature of the design or type of construction, or materially increases or decreases the cost of performance, a Supplemental Agreement acceptable to both parties shall be executed before work begins on the alteration. In the absence of a mutually acceptable Supplemental Agreement, the County may direct in writing that the work be performed by Force Account or at existing Contract prices, in accordance with the change-order and payment provisions of the Contract Documents. The Contractor shall begin work within fourteen (14) calendar days after receipt of the County-issued Notice to Proceed. The contract completion period shall be measured from receipt of the Notice to Proceed, as specified in the Notice to Contractors. The fourteen-day period allowed for commencement of work is included within, and does not extend, the contract completion period. If performance of all or any portion of the Work is suspended or delayed by the County in writing for an unreasonable period of time that was not originally anticipated, customary, or inherent to the construction industry, and the Contractor believes additional compensation and/or contract time is due as a result, the Contractor shall submit a written request for adjustment to the County within seven (7) calendar days after receipt of the notice to resume work. The request shall state the reasons for the adjustment and include supporting documentation. Upon receipt, the County will evaluate the Contractor’s request. If the County determines that the cost and/or time required for performance of the Contract has increased as a result of the suspension or delay, and that the suspension or delay was caused by conditions beyond the control of, and not the fault of, the Contractor, its suppliers, or subcontractors at any approved tier, and was not caused by weather, the County will make an appropriate adjustment, excluding profit, and modify the Contract in writing accordingly. The County will notify the Contractor in writing of its determination. No adjustment will be allowed unless the Contractor submits the request within the time prescribed. No adjustment will be allowed under this clause to the extent that performance would have been suspended or delayed by another cause, or where an adjustment is otherwise provided for or excluded under another term or condition of the Contract. MEASUREMENT AND PAYMENT The Department shall retain 5% of the gross value of the completed work as indicated by the current estimate certified by the County for payment. Final Payment: Upon completion by the Contractor of the work, including the receipt of any final written submission of the Contractor and the approval thereof by the County, the County will pay the Contractor a sum equal to 100 percent (100%) of the compensation set forth herein, less the total of all previous partial payments, paid or in the process of payment. Acceptance of final payment shall constitute a waiver of all claims by the Contractor arising out of the Contract, except those previously made in writing and identified by the Contractor as unsettled at the time of the final application for payment. In the event the Contractor fails to execute the Final Supplemental Agreement as prepared by the County because he disputes the amount of the final payment as stated therein, the amount due the Contractor shall be deemed by the Contractor and the County to be an unliquidated sum and no interest shall accrue or be payable on the sum finally determined to be due to the Contractor for any period prior to final determination of such sum, whether such determination be by agreement of the Contractor and the County or by final judgment of the proper court in the event of litigation between the County and the Contractor. The Contractor specifically waives and renounces any and all rights it may have under Section 13-6-13 of the Official Code of Georgia and agrees that in the event suit is brought by the Contractor against the County for any sum claimed by the Contractor under the Contract, for delay damages resulting from a breach of contract, for any breach of contract or for any extra or additional work, no interest shall be awarded on any sum found to be due from the County to the Contractor in the final judgment entered in such suit. All final judgments shall draw interest at the legal rate, as specified by law. Also, the Contractor agrees that notwithstanding any provision or provisions of Chapter 11 of Title 13 of the Official Code of Georgia that the provisions of this contract control as to when and how the Contractor shall be paid for The Work. Further, the Contractor waives and renounces any and all rights it may have under Chapter 11 of Title 13 of the Official Code of Georgia. Safety: The Contractor shall provide all necessary barricades and signage and take necessary precautions to protect buildings, general public and Contractor personnel. The Contractor shall at all times guard against damage or loss of Effingham County property or the general public and shall be held responsible for replacing or repairing any loss or damage to the satisfaction of The Effingham County Board of Commissioners. GENERAL CONSTRUCTION GUIDELINES 1.The contractor shall be required to coordinate his work schedule with the A/E and County during the course of the project. 2. Testing and payment for testing shall be handled as provided in the Contract Documents. Testing laboratory services required under Section 01 45 00 shall be selected and paid for by the Owner. The Contractor shall include in the bid all testing assigned to the Contractor under the technical specifications and shall pay for retesting when work fails to meet the specified requirements. 3. Effingham County does not commit to furnishing full-time inspection or testing of the work in progress or at material sources. Lack of inspection and/or testing by the County or A/E will in no way relieve the Contractor of his responsibility to provide quality workmanship in accordance with the Contract Documents. 4. The Contractor is required to submit shop drawings and material submittals to the A/E for review and approval prior to delivery and installation. Effingham County Regional Water Supply Facilities – 1.5 MG Elevated Water Tank Effingham County Board of Commissioners is soliciting sealed bids from qualified contractors for the construction of a new 1.5-million-gallon (MG) concrete composite elevated water storage tank as part of the Effingham County Regional Water Supply Facilities project. The Contractor shall furnish all labor, materials, equipment, supervision, transportation, testing, and incidental services necessary to construct a complete and fully operational elevated water storage facility in accordance with the approved construction plans, technical specifications, and Contract Documents prepared by Goodwyn Mills Cawood (GMC). The scope of work generally includes, but is not limited to, the following: Elevated Water Tank Construction: Design and construction of the tank foundation, ground improvements where required, fabrication and erection of the 1.5 MG concrete composite elevated water tank, structural components, interior slab, tank piping, appurtenances, access components, antenna corral, coatings, painting, and associated accessories. Site Preparation and Civil Improvements: Site clearing, excavation, grading, earthwork, trenching, backfilling, compaction, drainage improvements, gravel access driveway, gravel areas within the fenced facility, rip-rap, miscellaneous concrete improvements, and restoration of disturbed areas. Water System Piping and Connections: Installation of water mains, including 12-inch PVC piping, flanged piping, valves, fittings, valve vaults, hydrants, connections to the existing water distribution system, and associated appurtenances necessary for operation of the elevated tank. Electrical, Instrumentation, and SCADA Systems: Coordination and installation of electrical utility service, electrical panels, wiring, conduit, grounding and bonding, site and tank lighting, instrumentation, pressure monitoring equipment, SCADA controls, communications, and associated electrical and control system components. Site Security and Access: Installation of chain-link security fencing, gates, associated hardware, and other improvements necessary to provide secure access to the completed facility. Erosion Control and Environmental Compliance: Installation, inspection, maintenance, and removal of temporary erosion and sediment control measures; stormwater management and monitoring; compliance with applicable permits and regulatory requirements; and final stabilization and restoration of disturbed areas. Testing, Startup, and Project Closeout: Completion of required inspections, tank and piping testing, flushing, disinfection, bacteriological testing, electrical and SCADA system testing, startup, correction of deficiencies, final site cleanup, and submission of required closeout documentation. The Contractor shall coordinate construction activities with Effingham County, GMC, utility providers, and other contractors performing work associated with the Regional Water Supply Facilities project to minimize conflicts and maintain project progress. All work shall be performed in accordance with applicable federal, state, and local regulations, approved permits, construction plans, technical specifications, and Contract Documents. The scope described above is intended to provide a general overview of the project and shall not be considered an exhaustive listing of all work required. The Contractor shall be responsible for providing a complete, tested, and operational facility, including all materials, equipment, labor, and incidental work necessary to fulfill the requirements of the Contract Documents. Introduction Summary Background Contact Information Timeline Notice to Contractors EFFINGHAM COUNTY BOARD OF COMMISSIONERS 26322B12 , Effingham County Regional Water Supply Facilities 1.5 MG Elevated Water Tank NOTICE TO CONTRACTORS Bids will be received electronically by the Effingham County Board of Commissioners through the County’s eProcurement Portal, OpenGov, until 2:00 pm on Thursday, December 10, 2026 , Bids will be opened electronically through OpenGov following the submission deadline. The Work to be bid consists of furnishing all materials, labor and equipment for: The project includes furnishing all labor, materials, equipment, and services necessary to construct a 1.5-million-gallon concrete composite elevated water storage tank in Effingham County, Georgia. Work includes tank and foundation design and construction, site work, piping, tank erection and painting, electrical systems, supervisory control and data acquisition (SCADA), and related appurtenances, including testing and commissioning, in accordance with the project plans and specifications. MANDATORY PRE-BID CONFERENCE A MANDATORY pre-bid conference will be held at 1:00 pm on Tuesday, November 17, 2026 at Effingham County Board of Commissioners South Admin - Training Room 804 S. Laurel Street Springfield, GA 31329 Proposals will not be accepted from any firm that did not attend the pre-bid meeting for Effingham County Regional Water Supply Facilities 1.5 MG Elevated Water Tank . QUESTIONS Any questions that arise after the pre-proposal conference must be made in writing via the County's eProcurement Portal no later than 2:00 pm (Eastern Time) on Tuesday, December 1, 2026 . Questions will only be answered if submitted through the County's eProcurement Portal. Questions will be answered via the eProcurement Portal and/or via an addendum posted on the Effingham County eProcurement Portal on or before 2:00 pm on Friday, December 4, 2026 . BID BOND All bids shall be accompanied by bid security in an amount not less than five percent (5%) of the total bid amount, payable to or naming the Effingham County Board of Commissioners as obligee. Bidders may submit either an electronic bid bond through Surety2000 using the County’s eProcurement Portal or an original paper bid bond, certified check, or cashier’s check. Electronic bid bonds must be fully executed and submitted through the Portal before the bid submission deadline. A separate paper original is not required for an electronic bid bond accepted through the Surety2000 verification process. Bidders submitting paper bid security shall upload a copy with their bid and deliver the original to the Effingham County Procurement Office, 804 South Laurel Street, Springfield, Georgia 31329, before the bid submission deadline. The original shall be enclosed in a sealed envelope clearly marked with the project number and name. Mailing or shipping the original before the deadline does not satisfy this requirement unless it is received on time. Refer to the Vendor Questionnaire for detailed submission instructions. The BID BOND shall be subject to forfeiture to the Effingham County Board of Commissioners as liquidated damages if the BIDDER fails to execute the CONTRACT and provide the required PERFORMANCE BOND and PAYMENT BOND within fourteen (14) calendar days after receipt of the Notice of Award, subject to the terms of the bid bond and applicable law. A Notice to Proceed will be issued after receipt of the signed Contract, required Payment and Performance Bonds, and satisfactory proof of required insurance. The Contractor shall begin work within fourteen (14) calendar days after receipt of the County-issued Notice to Proceed. Payment will be made on a monthly basis for work performed the previous month, less retainage. The County will retain five percent (5%) of the gross value of the completed work as indicated by the current estimate approved by the Engineer. BIDDER'S CONFIRMATION The BIDDER is expected to examine the site of the proposed work, BIDDER’S CHECKLIST, INSTRUCTIONS TO BIDDERS, GENERAL CONDITIONS, SPECIFICATIONS, and AGREEMENT forms before submitting a BID. The Effingham County Board of Commissioners reserves the right to reject any and all Bids and to waive minor technicalities or informalities that do not materially affect the Bid or provide an unfair competitive advantage. Additionally, Effingham County may issue change orders altering the original scope of work to address changes or unforeseen conditions necessary for project completion, in accordance with the Contract Documents and applicable law. No Bid shall be withdrawn within sixty (60) days after the actual date of the opening thereof, except as permitted by applicable law. CONTRACT DOCUMENTS The CONTRACT DOCUMENTS may be examined at the following location: Effingham County Board of Commissioners, 804 South Laurel Street, Springfield GA, 31329. Copies of the CONTRACT DOCUMENTS may be obtained at: the County's eProcurement Portal. COMPLETION DAYS The Completion Date for this Contract shall be within 460 calendar days from receipt of Notice to Proceed. Instructions to Bidders INSTRUCTIONS TO BIDDERS 1.1 PURPOSE : The purpose of this document is to provide general and specific information for use in submitting a Bid to supply Effingham County with construction, equipment, supplies and/or services as described herein. All Bids/proposals are governed by the Code of Effingham County, and the laws of the State of Georgia. 1.2 HOW TO SUBMIT BIDS: All bids shall be submitted via the County's eProcurement Portal . BIDS NOT RECEIVED BY THE TIME AND DATE SPECIFIED WILL NOT BE OPENED OR CONSIDERED. 1.3 HOW TO SUBMIT AN OBJECTION: Objections from Bidders to this invitation to bid and/or these specifications should be brought to the attention of the County Purchasing Agent in writing. The objections contemplated may pertain to form and/or substance of the invitation to bid documents. Failure to object in accordance with the above procedure will constitute a waiver on the part of the business to protest this invitation to bid. 1.4 QUESTIONS: Any questions that arise after the pre-proposal conference must be made in writing via the County's eProcurement Portal no later than 2:00 pm (Eastern Time) on Tuesday, December 1, 2026 . Questions will only be answered if submitted through the County's eProcurement Portal. Questions will be answered via the eProcurement Portal and/or via an addendum posted on the Effingham Co

Published attachments
Addenda and notices
  • Addendum #1 · 1

    Supporting Attachment A – Sample Construction Contract has been replaced with a revised, project-specific contract. The revised Attachment A supersedes the prior version and is part of this ITB. All other terms and conditions remain unchanged.

  • Official Notice #1: Reminder - Mandatory Pre-Bid Meeting Today · 1

    This is a reminder that the Mandatory Pre-Bid Meeting for the Effingham County Regional Water Supply Facilities – 1.5 MG Elevated Water Tank project is scheduled for today, November 17, 2026, at 1:00 PM , in the South Administration Building Training Room. Please refer to the previously issued addendum for the updated meeting information.

  • Addendum #2 · 2

    Please use the See What Changed link to view all the changes made by this addendum. There was a conflict with our Pre-Bid meeting time/location and needed to move it to Tuesday, November 17th at 1:00 PM, same location, Effingham County Board of Commissioners, South Training Room, 804 S. Laurel Street, Springfield, GA 31329.

  • Addendum #3 · 3

    Please see the attached Pre-Bid Meeting Sign-In Sheet.

Public questions and answers
  • I notice the plans pages (per the index) go from Page 3 to Page 5, can you please confirm or clarify that Page 4 doesn't exist?

    Updated Title Sheet index. Will send link to updated plans & tech specs after 11/17/26 pre-bid meeting @ 1pm.

  • Will there be a site visit after the pre-bid meeting?

    Yes, there will be a site visit after the pre-bid meeting.

  • Do AIS, Buy American or any other domestic requirements apply to this contract?

    No. Based on the project’s current funding through GEFA’s state-funded Georgia Fund, AIS, Buy America/BABA, and other domestic-content requirements do not apply to this contract. All work remains subject to the plans, specifications, and applicable laws and regulations.

  • Is this bid subject to prevailing wages?

    No. The project is funded through GEFA’s Georgia Fund, a state-funded loan program. The solicitation does not include a prevailing wage determination or certified payroll requirement, and Davis-Bacon requirements apply to federally funded or assisted construction.

  • Please confirm this project is not exempt from sales tax, or clarify?

    The project is not exempt from applicable sales and use taxes on materials and other taxable items purchased by the Contractor for the Work. Under Georgia Department of Revenue guidance, contractors are treated as consumers and must pay applicable tax on construction materials, including materials used on government projects. Bidders should include applicable taxes in their bid.

  • Are there minority/disabled business use requirements subject to this bid/contract? If so, please provide further documentation.

    No minority, disadvantaged, or disabled business participation goals, set-asides, subcontracting percentages, or related certification requirements are included in this solicitation.

  • 3D Construction Company LLC dba Dig-It Site Works — Georgia UCP DBE certified; prospective foundation (ACIP) and site-civil subcontractor. We are pricing the foundation drilling package (Bid Item E) and the site-civil package (Bid Items B, C, F–N and Q–T). Questions from the bid documents: Item H quantity — plan stationing vs. proposal form. Sheet C-301 stations the 12-inch C900 run from STA 0+00 to STA 2+23 — approximately 223 LF. Please confirm the quantity carried on the OpenGov proposal form for Bid Item H, and state which governs for payment if the form quantity differs from the plan stationing.

    Change to “12" C900 DR 18 PVC Water Main (Includes all Rest. Jt.)” Change quantity to “223 LF”. Revised Plans and Technical Specifications will be posted when OpenGov questions are complete.

  • Item H pipe class — DR 25 vs. DR 18. Spec §01 20 00 ¶1.2.H describes the item as "12-inch C900 DR 25 PVC Water Main," while Sheet C-301 calls out "PROPOSED 12-inch C900 DR 18 REST. JT. PVC" for the same run. Which dimension ratio governs for bidding and construction?

    Plans are correct, changed to DR 18 “12" C900 DR 18 PVC Water Main (Includes all Rest. Jt.)” in Technical Specifications and Bid Form.

  • Item K valve type — gate vs. butterfly. Spec §01 20 00 names Bid Item K "12-inch Gate Valve, Buried Service," and Sheet C-301 calls out two 12-inch gate valves plus the 12-inch gate valve furnished with the tapping sleeve under Item L. Please confirm every buried 12-inch valve on the project is a gate valve, and identify any location — under Item G, Item K, or elsewhere in the yard piping — where a butterfly valve is required.

    12" Gate Valves are correct. Changed in Bid Form.

  • Item M fence quantity. Sheets C-101/C-202 call out "805 feet of 3-strand barbed wire, chain link fence," but no total fence length is stated separately in the plans. Please confirm the proposal-form quantity for Bid Item M and whether the fence measurement and the barbed-wire measurement are the same length.

    Fence quantity change to 690 LF. Changed in Bid Form and Plans.

  • Item Q silt fence — two different totals. Sheet C-202 shows 360 LF of Type "NS" plus 460 LF of Type "S" silt fence at the tank site, while the ES&PC notes on Sheet G-002 estimate 1,259 LF of Type "NS" silt fence project-wide. Bid Item Q is lump sum: please state the governing silt-fence extent the lump sum must cover.

    Revised C-203 to 510 LF of Type “NS” and 460 LF of Type “S” silt fence. All silt fencing shall be covered under “Erosion and Sediment Control”. Changed G-003 note to 970 LF.

  • Foundation excavation — Item E vs. Items B, C, and P (interface). The foundation is designed by the tank contractor and carried inside Bid Item E (§33 16 11 ¶1.3.D.4; §01 20 00 ¶1.2.E), but the documents do not draw the line between the foundation work and the site items. Please confirm that excavation, spoil disposal, backfill, and compaction for the contractor-designed pile cap/ringwall — and the 2-inch concrete working slab permitted by §33 16 11 ¶3.3.A — are inside Item E and are not payable under Item B (Clearing & Grubbing), Item C (Site Grading), or Item P (Misc. Concrete).

    All the work items described above shall be included into the “1.5 MG Concrete Composite Elevated Water Tank” and alternate bid item.

  • Foundation work area vs. limits of disturbance. Sheet C-202 fixes the limits of disturbance at 0.83 acres. ACIP installation needs room for the CFA rig, crane, grout plant, cage staging, and spoil handling. Please confirm the foundation work fits inside the stated limits of disturbance; if a larger work area is intended, identify it and state who carries its erosion-control measures under Item Q and its restoration.

    All the work described above shall be included inside silt fence area excluding Blue Jay Rd. R/W. Must stay out of the wetlands or a USACE permit is required.

  • Two tank systems — basis of award and the $11,000,000 figure. The Project Manual carries two complete, mutually exclusive systems — §33 16 11 (Composite) and §33 16 19 (Spheroid Steel) — each with its own with-proposal qualification package, and the foundation design basis differs between them. The Sample Agreement, Art. 1, describes the tank as "of the type selected for award," and Art. 5 prints a price of $11,000,000.00. Please confirm: (a) the proposal form solicits a separate lump-sum price for each tank type and the County selects the type at award; (b) the $11,000,000 figure is an estimate/placeholder only, not a budget cap; and (c) whether the §33 16 11 ¶1.4.A package, the §33 16 19 ¶1.1.C package, or both must accompany the proposal.

    Each proposed elevated water tank is a separate lump sum bid Effingham County will decide which type of tank to award.

  • Insurance schedule and the missing General/Supplementary Conditions. The Bidder's Checklist requires a Certificate of Insurance with the proposal, but no coverage types or limits appear anywhere in Attachments A–E, and the General Conditions and Supplementary Conditions listed in Agreement Art. 9.01.A were not included in the posted documents. Please issue the insurance schedule — including any professional or pollution liability required for the design-build foundation scope — and confirm whether the General/Supplementary Conditions will be posted by addendum.

    The County’s insurance requirements are set forth in Sections 5.12–5.15 of the ITB and are incorporated into the Sample Contract through Agreement Article 9.01.A. They include $1 million general liability, statutory workers’ compensation with $500,000 employer’s liability, $1 million auto liability, $1 million professional liability for design services, and builder’s risk at 100% of contract value. The specifications require pollution control but do not require pollution liability insurance. The bid-stage Certificate of Insurance is proof of coverage and need not name the County. If awarded, the Contractor must provide an updated certificate before work begins, listing the County as certificate holder.

  • Geotechnical record — where the borings live. Spec §01 81 00 ¶1.2.C states that boring results and soil improvement recommendations are "included in the plans," but the 29-sheet plan set contains no boring logs; the boring and CPT records appear only in the appendix to the Project Manual (GMC Report GSAV250004, July 7, 2026, and Addendum, July 21, 2026). Please confirm that appendix report, as posted, is the complete geotechnical record bidders may rely on for foundation pricing, and that no additional borings exist.

    All Geotechnical information is listed in the Project Manual Appendix and not on the plans.

  • ACIP grout requirements — specification gap. No section in Divisions 03, 31, or 33 sets auger-cast pile grout strength, mix design, or cage requirements; the only grout criteria in the documents are the geotechnical report's grout factor (≥ 1.2) and pressure-head (≥ 5 ft) rules. Please confirm these parameters are set by the tank contractor's foundation designer under §33 16 11 ¶1.3.D.4 and will not be supplemented by addendum.

    Yes, auger cast piles are part of delegated design for tank foundation designer.

  • The bid specifications do not state whether a bid opening link will be provided or if bid results will be posted at a certain time/date. Will a bid opening link be provided?

    Effingham County conducts all bid submissions and openings electronically through OpenGov. There will not be a public bid opening or a bid opening link. Bid results will be available through OpenGov following the bid closing and review process.

  • SCADA System 40 60 00 – 4 of 13 No. 44 states the System Integrator must provide evidence of prior production with the proposal. Please advise if this can be submitted post-bid.

    Yes.

  • Section 33 16 19 Item 1.1.C Submittals states no bid will be considered unless a list of five "Pedesphere" style elevated tanks constructed within the last ten years, a preliminary drawing of the tank showing major dimensions and plate thickness upon which the bid is based and a foundation design drawing showing preliminary dimensions and approximate quantities of concrete and reinforcing steel is submitted with the bid. Is it a requirement for the contractor to bid BOTH styles of the tank? Or can the contractor bid on only ONE style of the tank?

    Contractor shall submit base bid and optional on alternate bid Spheroid Tank.

  • With regards to the 'Progress Photographs' section of the 'Submittals' specification, the project requires construction photographs, seemingly for support of each pay request. Section 1.9.A of 01 33 00, says photographs must be by an 'experienced' photographer and Section 1.9.C.1 states the photographs must be 'high resolution digital photographs'. Is the intention of this specification section for the bidder to hire a photographer to comply with the 'experienced' photographer requirement? Or would a member of our crew be acceptable? Similarly, is there a specific make / model, etc. of camera or device needed to appropriately produce the requirement for 'high resolution digital photographs'? Or can photos taken with a newer model cell phone suffice for this? Essentially, please clarify if a crew member using a cellphone is acceptable for photos on this project, or do the bidders need to account for something more.

    Professional Photographer not required, cell phone is acceptable that produces a minimum 12 megapixel photo.

  • Section 33 16 11 Elevated Composite Water Storage Tank, Part 2 – Products, 2.6 Appurtenances and Accessories, F. Concrete Support Structure Doors, 2. Overhead Vehicle Door indicates that the overhead door is to be 12’ wide x 10’ high. Can you confirm that a 10’ wide x 12’ high overhead door size is acceptable?

    10' wide x 12' high overhead door is acceptable.

  • Section 33 16 11 does not describe the level of weld seam preparation. We suggest the following clarification, which is industry standard: ‘Grinding of weld contour shall approximate Condition D of NACE Standard SP0178’. Can you confirm the Bidder is to proceed per this clarification?

    Yes.

  • Section 33 16 11, Item 2.6.H.2 specifies a drip pan located under the access tube (typically attached to the underside the walkway) to collect any condensate dripping from the access tube. This detail has been improved and is no longer done. We suggest paragraph 2 be replaced with the following which is current industry standard: ‘The access tube shall incorporate a 2” x 2” channel to collect condensation that may form on the interior surface of the access tube. A flexible 3/2” PVC hose complete with backflow preventer shall drain the channel to the overflow pipe’. Can you confirm the Bidder can replace the drip pan with a 2”x2” channel to collect the condensation?

    This is acceptable.

  • Section 33 16 11 Item 2.7.D states that the Contractor is to provide Andrews Plates and cell rings “as shown on the drawings”. However, the drawings do not show them. Can you confirm Andrews Plates and cell rings are NOT required for this project?

    Section 33 16 11 section 2.7 will be revised to require antenna corral not cell ring and Andrews plates.

  • If the Andrews Plates and cell rings are required, can a drawing be provided?

    See answer #25.

  • Section 01 45 00 Item 1.3 states that the Owner will pay for concrete testing. However, Section 33 16 11 Item 3.6.A.3 states that the Contractor is to pay. Can you confirm that the Owner will provide and pay for concrete testing?

    Yes, Owner will pay for first test. The cost of retesting any item that fails to meet the requirements of these Specifications shall be paid for by the Contractor. Retesting shall be performed by the testing laboratory working for the Owner. Tech Spec Section 33 16 11 Item 3.6.A.3 will be revised.

  • Section 33 16 11 Item 2.6.H.1 calls for a 48” access tube, however, there are antenna provisions for substantial antennas. A 48” access tube is not large enough to accommodate the antenna provisions. Can you confirm a 60”, not 48”, access tube is required for this project?

    60" access tube is acceptable.

  • Drawing Sheet C-303 – Elevation Note calls for OSHA compliant safety climb (cable style). Our standard design utilizes an OSHA compliant aluminum rigid rail ladder safety device. Can you confirm either a cable or rigid rail aluminum ladder safety devices is acceptable?

    See Section 33 16 11 - Elevated Composite Water Storage Tanks Safe Climbing Device/Safety Equipment 1. OSHA compliant safe climbing system shall be provided on all ladders. Two sleeves with snap hooks shall be provided that are designed to be operated with the system. Two harnesses with shock resistant lanyards shall be provided with the system. 2. Exterior ladders shall be equipped with a lockable metal anti-climb ladder guard with a minimum height of 72-inches.

  • Drawing Sheet C-303 – Elevation Detail shows an upper return at the intersection of the tank side wall and the tank roof in one image but does not show the upper return in the section view image. This detail is architectural in nature, adds considerable cost. Can you confirm the upper return is not required?

    Upper return not required.

  • Drawing Sheet C-902 – The Gravel Drive & All Areas Inside Fence Detail states that the soil is to be stabilized 24" deep. Can you confirm that we are to scarify, dry, and compact 24" deep to satisfy this requirement?

    Gravel pavement shall be used as a driveway and around the elevated water tank. Install geotextile filter fabric to separate the subgrade soils and the dense graded aggregate base stone. Gravel surfacing consists of a minimum of 6-inches of aggregate base course. The top 6-inches of the subgrade should be compacted to a minimum of 98 percent compaction per standard Proctor maximum dry density (AASHTO T99/ ASTM D698). The aggregate base stone should be a dense-grade aggregate based as outlined in Section 815, Group II compacted to at least 98 percent modified Proctor maximum dry density (AASHTO T 180/ ASTM D1557).

  • Drawing Sheet C-902 – The Gravel Drive & All Areas Inside Fence Detail - Due to the wet nature of the site, it is unlikely that we will be able to dry the soil. Can you confirm that we are to remove the 24" of unsuitable soil and replace with 24" of suitable soil?

    See answer #31.

  • In the original Bid Documents, the Notice to Bid had Liquidated Damages set at $1,000 per day. However, Addendum 1 replaced this section and liquidated damages are no longer addressed in this section. Can you confirm the Liquidated Damages are to be $1,000 per day?

    Liquidated damages remain $1,000 per calendar day, as specified in Article 4, Section 4.01 of the Sample Construction Contract.

  • Can you confirm funding is in place for this project?

    Yes, funding has been allocated for this project.

  • Can you confirm the budget amount for this project?

    The budget amount will not be disclosed during the competitive bidding process.

  • What is planned Notice of Award date for the project?

    The Notice of Award is anticipated in January 2027, following bid evaluation and approval by the Board of Commissioners.

  • What is the planned Notice to Proceed date for the project?

    The Notice to Proceed is anticipated to be issued in February 2027.

  • Can you describe the process or events (i.e. approval by council, board of directors, etc.) that must occur and anticipated dates and durations that must occur in order to award this project?

    Following the December 10, 2026, bid closing, the County will review and evaluate bids and prepare a recommendation for approval by the Board of Commissioners. Board approval is anticipated in January 2027, followed by issuance of the Notice of Award. The Notice to Proceed is anticipated in February 2027.

  • Is a Building Permit required for the project or for just the elevated tank?

    County Building Permit is required. The fee will be waived, paid for by the Owner.

  • If a Building Permit is required will the associated permit and review fees be waived?

    Yes, all County fees will be waived if it is a County Permit.

  • If a Building Permit is required and the Contractor is to pay all associated fees, can a fee schedule be provided so Bidders can include the appropriate costs within the bid pricing?

    See answer #39.

  • If a building permit is required, can you please advise as to what forms and documents must be provided?

    See answer #39.

  • Once a building application has been submitted, typically how long is the review process?

    See answer #39.

  • Can you confirm that the Owner has obtained the necessary approvals and permits required to start construction?

    Yes, all approvals and permits have been obtained.

  • Are there any governing agencies (federal/state/local agencies other than the building permit department) that must review and approve the project drawings prior to the start of construction? If so, who are these agencies and what is the anticipated duration for their review period?

    See answer #39.

  • Can you confirm that the Owner currently owns the property (or properties) where work is to be performed? If not, can you provide information on the timing in which ownership will be obtained?

    Yes, the Owner owns the property.

  • Can you confirm that the Owner currently owns and/or otherwise possess all required easements or permissions to work on or access the property (or properties) where the work is to be performed? If not, can you provide information on the timing in which these easement or permissions will be obtained?

    See answer #46.

  • Due to the nature of tank erection work and the travel distance for our field personnel, working nights is advantageous for the project from both a cost and schedule perspective. This is even true if the work allowed at night is restricted to non- inspected work. If night work is not approved during the bidding phase, it will negatively affect the bid by adding significant costs and duration to the project. Can you confirm that night work will not be restricted?

    Restricted Nighttime Hours: Under Effingham County noise control provisions (Section 30-38), operating tools or equipment for construction, drilling, demolition, or preventive utility maintenance between 7:00 p.m. and 7:00 a.m. is prohibited when it creates a noise disturbance across a real property boundary or within a noise-sensitive area. Daytime Noise Limits: Outside of those nighttime hours, construction and related work still cannot create a noise disturbance across a property boundary or within a noise-sensitive area, with sound levels exceeding 85 dBA deemed a noise disturbance under the ordinance.

  • The ITB document, Section 2.7, lists the execution schedule as completion of the project within 460 days of the NTP. As it does not differentiate between Substantial Completion and Final Completion, are we to assume SC and FC are combined as one date? Please note, in some areas of the General Conditions such as Section 5.15.2 and 5.23, it mentions a 'Certificate of Substantial Completion'. Also, Sections 1.4 and 1.7 of the Sample Contract reference 'Substantial Completion' as a concept. Please clarify if Substantial Completion and Final Completion are intended to be combined or different dates.

    The 460 calendar days from the Notice to Proceed represents the total contract duration for Final Completion. Substantial Completion is a separate milestone but must also be achieved within the 460-day contract period.

  • The ITB document, Section 2.7, lists the execution schedule as completion of the project within 460 days of the NTP. As the water industry has been extremely active in the recent past, this may not be enough time to complete this tank project. It was noted in the prebid meeting that the overall project must be in service by the 'end of 2029'. Assuming the NTP for the tank project happens in February 2027, it stands to reason there may be some additional time available for the execution of this tank project. Would the project consider a longer timeframe for execution schedule? We would suggest something closer to 650 days for this project.

    Bid as specified.

Plain text

OpenGov categories

  • 91340 · Construction, Pipeline
  • 91356 · Construction, Utility/Underground Projects
  • 91360 · Construction, Water System/Plants, Main and Service Line
  • 91430 · Concrete
  • 91438 · Electrical