Pursuant to the Port St. Lucie City Code of Ordinance 35.07, this electronic Request for Qualifications (RFQu) is being issued to establish a continuing services contract with a minimum five (5) qualified proposers who will provide Engineer Continuing Services Contract for Utility Projects to the City of Port St. Lucie (hereinafter, “City”) as further described in this RFQu. The purpose of this RFQu is to provide the City with qualified engineering consultants on an as-needed basis to support the planning, design, permitting, construction administration, inspection, and management of utility and infrastructure projects. The contract allows the City to efficiently deliver Capital Improvement Program projects, respond to emergencies, maintain compliance with regulatory requirements, and obtain specialized technical expertise while reducing procurement time and administrative costs. Scope of Work Scope of Work Definitions of Acronyms For the purposes of this Solicitation and the resulting Contract, the following acronyms and abbreviations shall have the meanings indicated below. These definitions are provided to ensure clarity throughout the Scope of Work and all associated documentation. ACOE – U.S. Army Corps of Engineers CAD – Computer-Aided Drafting CEI – Construction Engineering and Inspection CIP – Capital Improvement Plan CMOM – Capacity Management, Operations, and Maintenance DEP – Florida Department of Environmental Protection EOR – Engineer of Record FDOT – Florida Department of Transportation FEMA – Federal Emergency Management Agency FHWA – Federal Highway Administration FDEP – Florida Department of Environmental Protection FPL – Florida Power & Light GIS – Geographic Information System GPS – Global Positioning System MCC – Motor Control Center MS4 – Municipal Separate Storm Sewer System NPDES – National Pollutant Discharge Elimination System NRCS – Natural Resources Conservation Service NTP – Notice to Proceed RFI – Request for Information R/W – Right-of-Way SCADA – Supervisory Control and Data Acquisition SORP – Sanitary Sewer Overflow Response Plan SFWMD – South Florida Water Management District SRF – State Revolving Fund TMDL – Total Maximum Daily Load USD – Utility Systems Department WIFIA – Water Infrastructure Finance and Innovation Act Scope of Work The Consultant shall provide professional engineering services for projects within the utility work program and to support residential and commercial development consisting of studies, design, permitting, and certification for all types of water and wastewater pipelines, facility improvements, lift station rehabilitation, pump station improvements, repairs, and upgrades to the water and wastewater utility system. The City will determine the exact scope of work under this Contract on a project-by-project basis, which may include, but is not limited to, the categories and types of services listed below. Specific tasks for this project are defined per project. In addition, all projects assigned under this contract must comply with all RFQu requirements set forth herein. The City intends to procure the services of no fewer than five (5) Professional Engineering firms to provide services for the City’s adopted Utility Capital Improvement Plan (CIP), Utility Master Plan, and/or any other utility-related projects and any subsequent amendments. The continuing contracts will be utilized for projects and planning/study-related activities in accordance with Section 287.055, Florida Statutes. Professional engineering firms must be registered in the State of Florida and maintain staff with the appropriate qualifications and experience necessary for each individual project. In addition, firms must be able to comply with all applicable federal guidelines and requirements, as several CIP projects are federally funded. The following represents the types of projects for which the Utility Systems Department may require professional engineering, scientific, and technical services, including but not limited to: SERVICES The scope of this Contract covers the following services, among others: Distribution and Collection Systems Water distribution system design, including pipelines, appurtenances, and related improvements Raw water main design, including transmission mains, appurtenances, and related improvements Reuse water main design, including distribution mains, appurtenances, and related improvements Wastewater collection system design, including gravity mains, force mains, low-pressure force mains, and related improvements Water & Wastewater Facilities Water treatment facility design, upgrades, and improvements Wastewater treatment and reclamation facility design, upgrades, and improvements Raw water well facility design, testing, and upgrades Pump and repump station facility design and upgrades Membrane system design and replacement Fluid metering facility design and upgrades Electrical, Instrumentation & Controls Electrical system and motor control center (MCC) design and upgrades SCADA system design, modification, and upgrades Control panel design Instrumentation and controls design and upgrades Structural & Geotechnical Structural engineering design and evaluation Geotechnical investigation and engineering support Surveying & Mapping Boundary, topographic, utility, R/W, and easement surveys GIS and GPS mapping services Legal descriptions and sketches for easement and R/W acquisition Construction Administration, Management, and Inspections (CEI) Conducting and/or attending preconstruction meetings. Review and approval of shop drawings, products, submittals, RFI, verified quantities, and similar items during the construction-related phase. Review/ prepare pay applications, change orders, schedules, progress reports, and as-built drawings Construction contract administration. Construction engineering and inspection services. Coordination/provision of record drawings and as-built drawings. Prepare and certify utility systems, if needed. Observe construction projects, prepare daily inspection reports, take photographs, and provide to the City's Project Manager. Additional engineering services may be required during construction. OTHER SERVICES / STUDY ACTIVITIES Planning & Studies Prepare various concepts, alternative analyses, and feasibility studies for Capital Projects as needed. Prepare various facility plans and evaluation studies for Capital Projects as needed. Analyze alternative design concepts and prepare technical reports as needed. Utility master planning and CIP development Facility evaluation and condition assessment Hydraulic and water quality modeling Water and wastewater treatment pilot plant evaluations and studies Asset management, data acquisition, and syst Introduction Purpose of Procurement Pursuant to the Port St. Lucie City Code of Ordinance, Section 35.07 , and Section 287.055 , Florida Statutes (Consultants’ Competitive Negotiation Act), the City of Port St. Lucie, a Florida Municipal corporation (“City”) is requesting Proposals from qualified firms to provide Professional Engineering Services for Engineer Continuing Services Contract for Utility Projects . This electronic Request for Qualifications (RFQu) has been developed to solicit responses from consulting firms (or teams of firms) proven to be qualified and experienced in providing professional Engineering Services. A descriptive overview of the City can be found at About PSL | City of Port St. Lucie, FL (cityofpsl.com). Please visit the City’s website to familiarize yourself with how our city is structured and operates. Please contact the Issuing Officer with any questions. Overview of the RFQu Process The objective of the RFQu is to select a qualified Proposer (as defined by Section 1 – “Purpose of Procurement”) to provide the services outlined in this RFQu to the City. This RFQu process will be conducted to gather and evaluate responses from Proposers for potential award. All qualified Proposers are invited to participate by submitting responses, as further defined below. After evaluating all Proposers’ responses received prior to the closing date of this RFQu and following negotiations (if any) and resolution of any contract exceptions, the preliminary results of the RFQu process will be publicly announced (or posted) to the electronic bidding system, to include the names of all participating Proposers and the evaluation results. Subject to the protest process, final Contract award(s) will be publicly announced thereafter. NOTE TO PROPOSERS: The general instructions and provisions of this document have been drafted with the expectation that the City may desire to make one award or multiple awards. For example, this document contains phrases such as “contract(s)” and “award(s).” Please refer to Section 1.1 – “Purpose of Procurement,” and Section 6 – “Proposal Evaluation, Negotiations, and Award,” for information concerning the number of Contract awards expected. Schedule of Events The Schedule of Events set out herein represents the City’s best estimate of the schedule that will be followed. However, delays to the procurement process may occur, which may necessitate adjustments to the proposed schedule. If a component of this schedule, such as the close date, is delayed, the rest of the schedule may be shifted as appropriate. Any changes to the dates up to the closing date of the RFP will be publicly posted prior to the closing date of this RFQu. After the close of the RFQu, the City reserves the right to adjust the remainder of the proposed dates, including the dates for evaluation, negotiations, award, and the Contract term, on an as-needed basis, with or without notice. Release of RFQu: November 2, 2026 Question Submission Deadline: November 16, 2026, 5:00pm Question Response Deadline: November 23, 2026, 4:00pm Response Submission Deadline: December 7, 2026, 3:30pm Microsoft Teams meeting Join: https://teams.microsoft.com/meet/2679124870099571?p=QIlMeS3j3r5NjTcsLC Meeting ID: 267 912 487 009 957 1 Passcode: qd9yE9Xd ________________________________________ Dial in by phone +1 561-437-3554, Phone conference ID: 689 299 456# Evaluation Phase (Non-Mandatory): January 12, 2027, 1:00pm Microsoft Teams meeting Join: https://teams.microsoft.com/meet/2609359071423907?p=PXHj5OmrYqU1lhNoXl Meeting ID: 260 935 907 142 390 7 Passcode: Vp92jM7h ________________________________________ Dial in by phone +1 561-437-3554, Phone conference ID: 334 919 249# The City reserves the right to proceed to award without further discussions after receipt of the initial proposals, in which case, evaluation committee reviews, negotiations, and proposal revisions may not be required. Official Issuing Officer (Procuring Agent) Max Previlon , Procurement Contracting Officer III O. 772-871-7337 mprevilon@cityofpsl.com Definition of Terms Please review the following terms: Consultants’ Competitive Negotiation Act (“CCNA”) - Section of the Florida Statutes that governs the acquisition of professional architectural, engineering, landscape architectural, or surveying and mapping services. See section 287.055, Florida Statutes . Consultant(s) - companies desiring to do business with the City (Also called “Engineer,” “Bidder,” “Proposer,” “Firm,” "Respondent," or “Offeror.”) City of Port St. Lucie (“City”) - the governmental entity identified in Section 1.1 “Purpose of Procurement" of this RFQu. Contract - agreement entered into between City and the awarded Proposer. Immaterial Deviation - does not give the Proposer a substantial advantage over other Proposers. Material Deviation - gives the Proposer a substantial advantage over other Proposers and thereby restricts or prevents competition. Procurement Management Division (“PMD”) - the City department that is responsible for the review and possible sourcing of all publicly sourced solicitations. Responsible – means the Proposer, whether a company or an individual, has the financial and technical capacity to perform the requirements of the solicitation and subsequent Contract which will assure good faith performance of the Contract. Responsive – means the Proposer, whether a company or an individual, has submitted an offer which conforms in all material respects to the requirements set forth in the solicitation. Sourcing Platform/Electronic Bidding System - OpenGov. Any special terms or words which are not identified in the City’s RFQu Document may be identified separately in one or more attachments to the RFQu. Please download, save and carefully review all documents in accordance with the instructions provided in Section 3 – “Instructions to Proposers,” of this RFQu. Contract Term The Initial term of the contract(s) is for three (3) calendar years from the execution date. The City shall have two (2), one (1) year option(s) to renew, which options shall be exercisable at the sole discretion of the City. Renewal(s), if provided and selected solely by the City, will be accomplished through the issuance of Contract Amendment. In the event that the contract(s), if any, resulting from the award of this RFQu shall terminate or be likely to terminate prior to the making of an award for a new contract for the identified products and/or services, the City may, with the written consent of the awarded Proposer(s), extend the contract(s) for such period of time as may be necessary to permit the City’s continued supply of the identified products and/or services. The Contract(s) may be amended in writing from time to time by mutual consent of the parties. Unless this RFQu states otherwise, the resulting award of the Contract(s) does not guarantee volume or a commitment of funds. Hours of Service The standard hours of work allowed in the City’s rights-of-way are from 7:00 a.m. to sundown Monday through Friday. Any work performed by the Consultant outside of the aforementioned time limit requires special authorization by the City and requires that the Consultant obtain a noise permit from the Port St. Lucie Police Department (PSLPD). All equipment operated at night shall comply with the noise levels established by the City of Port St. Lucie noise ordinance. Any additional costs associated with work outside of the hours of work allowed shall be borne by the Consultant. This shall include, but is not limited to, costs of inspection, testing, police assistance, and construction administration. All night, Saturday, Sunday, and/or Holiday work must be authorized by the City and requires that the Consultant obtain a noise permit from the PSLPD. All night work within the City’s rights-of-way requires a minimum forty-eight (48) hour prior notice to the City. This clause shall not pertain to crews organized to perform maintenance work on equipment or to operate and maintain special equipment such as dewatering pumps, which may be required to work twenty-four (24) hours per day. Instructions to Proposers This section contains general business requirements. By submitting a response, the Proposer is certifying its agreement to comply with all the identified requirements of this section and that all costs for complying with these general business requirements are included in the Proposer’s submitted pricing. By submitting a response to the RFQu, the Proposer is acknowledging that the Proposer: Has read the information and instructions, and Agrees to comply with the information and instructions contained herein. General Information and Instructions 3.1.1 Familiarity with Laws and Regulations It is the responsibility of responding Proposers to be familiar with all Federal, State, and local laws, ordinances, rules, and regulations, that may affect the work. Ignorance on the part of the Awarded Contractor will in no way relieve it from Contract responsibility. 3.1.2 Restrictions on Communicating with Staff/ Cone of Silence From the issue date of this RFQu until the time of City Council's approval of the award or the City Manager's approval when proposal amount is below the required formal solicitation threshold (or the RFQu is officially canceled), Proposers are not allowed to communicate for any reason with any City staff or elected officials except through the Issuing Officer named herein, during the Bidders'/Offerors’ conference (if any), as defined in this RFQu, or as provided by existing work agreement(s). This is commonly known as a Cone of Silence during the procurement process as identified in the City Code of Ordinances, Section 35.13 . Prohibited communication includes all contact or interaction, including but not limited to, telephonic communications, emails, faxes, letters, or personal meetings, such as lunch, entertainment, or otherwise. The City reserves the right to reject the response of any Proposer violating this provision. Further information on this topic can be found on the Cone of Silence and RFQu Communication Document. 3.1.3 Submitting Questions All questions concerning this RFQu must be submitted in writing on the OpenGov Platform during the Question and Answer open period. Please select the Question and Answer tab in the RFQu project and click the "Ask Question" option. Once the question has been entered, select the "Submit Question" button. Enter a subject in the Subject field and then type the question in the Question field below. Once finished, select "Submit." No questions other than written will be accepted. No response other than written will be binding upon the City. All Proposers must submit questions by the deadline identified in the Schedule of Events for submitting questions. Proposers are cautioned that the City may or may not elect to entertain late questions or questions submitted by any other method than as directed by this section. 3.1.4 Attending Pre-Proposal Conference The Pre-Proposal Conference or any other information session (if indicated in the Schedule of Events) will be held at the offices referred to in Section 1.3 - “Schedule of Events” of this RFQu. Unless indicated otherwise, attendance is not mandatory, although Consultants are strongly encouraged to attend. However, in the event the conference has been identified as mandatory, then a representative of the Consultant must attend the conference in its entirety to be considered eligible for Contract award. The Consultant is strongly encouraged to allow ample travel time to ensure arrival in the conference meeting room prior to the beginning of any mandatory conference. The City reserves the right to consider any representative arriving late to be “not in attendance.” Therefore, all Consultants are strongly encouraged to arrive early to allow for unexpected travel contingencies. 3.1.5 The City's Right to Request Additional Information- Proposer's Responsibility Prior to Contract award, the City must be assured that the selected Proposer has all the resources to successfully perform under the Contract. This includes, but is not limited to, adequate number of personnel with required skills, availability of appropriate equipment in sufficient quantity to meet the on-going needs of the City, financial resources sufficient to complete performance under the Contract, and experience in similar endeavors. If, during the evaluation process, the City is unable to assure itself of the Proposer’s ability to perform, if awarded, the City has the option of requesting from the Proposer any information deemed necessary to determine the Proposer’s responsibility. If such information is required, the Proposer will be no

Published attachments
Addenda and notices
  • Addendum #1 · 1

    This Addendum is issued to update the Indemnification/Hold Harmless provisions contained in Section 4.1 of the Solicitation Document and Section IX of the Sample Contract . Please use the See What Changed link to view all the changes made by this addendum.

  • Addendum #2 · 2

    Please use the See What Changed link to view all the changes made by this addendum.Please see the summary table outlining the changes included in this addendum. Amendments to Section 2 – Scope of Work No. Location Current Text Revised Text 1 Section 2, Subsection 2.1, “Scope of Work,” first paragraph, sentence 1 “The Consultant shall provide professional engineering services for projects within the utility work program consisting of studies, design, permitting, and certification…” “The Consultant shall provide professional engineering services for projects within the utility work program and to support residential and commercial development consisting of studies, design, permitting, and certification…” 2 Section 2, Subsection 2.1, “Scope of Work,” first paragraph, sentences 3 and 4 “Specific tasks for this project are defined per project. Specific tasks for this project are defined per project. In addition, all projects assigned under this contract…” “Specific tasks for this project are defined per project. In addition, all projects assigned under this contract…” (Duplicate sentence deleted.) 3 Section 2, Subsection 2.1, “Services,” Technical & Operational Support, fourth bullet “Building Division plans review and inspection services” “Building Division and Utility Commercial Development Division plans review and inspection services” 4 Section 2, Subsection 2.1, “Services,” Design Support, sixth bullet “Participate in the site and development processes.” “Participate in the site and development plan review processes , including those of the Building Division and Utility Commercial Development Division .” 5 Section 2, Subsection 2.1, “Services,” Miscellaneous Support, last bullet “Perform other duties as needed; services dictated by the needs of the CIP and other specific projects” “Perform other duties as needed; services dictated by the needs of the CIP , Commercial Development Division and other specific projects” Amendments to Scoring Criteria – Proposer’s Experience Amendment #6 - Section 3, Subsection 3.3, “Proposal Format,” Tab 2 – Proposer’s Experience. 7. Optional – Subconsultant Information. The Proposer may submit information on up to three (3) subconsultants. Each subconsultant is limited to a

Public questions and answers
  • Are firms expected to provide all the services listed under the scope of work or would firms offering only specialized services (i.e. Structural & Geotechnical or Surveying & Mapping) also be considered?

    Yes, the Utility Systems Department anticipates that proposing firms will provide the full range of services identified in the scope of work, either directly or through a team of subconsultants.

  • Should we include Experience (Tab 2 - Min 5 max 10) of our subconsultants as well as prime?

    Yes

  • It appears in the RFQ PDF, the column for "Criteria" under Scoring Criteria is cut off. Can the City please provide a new version of the Scoring Criteria to ensure readability?

    Thank you for bringing this to our attention. The scoring criteria can be accessed through the solicitation link provided below. After opening the solicitation, please click on "Project Documents" and then navigate to Section 7 – Scoring Criteria, where the information is available in a readable format. https://procurement.opengov.com/portal/cityofpsl/projects/295030/document?section=2837599

  • Would 10-point font be acceptable for captions and text within graphics?

    Yes

  • Will the City agree that the Indemnification obligation shall comply with Fla Statutes Chapter 725.08, wherein if it does not, pursuant to sub-section (2) of that statute it is void as a matter of pubic policy?

    Please see Addendum #1.

  • Where a Consultant cannot have the City be an additional insured on its Professional Liability insurance, will the City agree to this exception?

    May you please clarify and identify the specific sentence and or section you are referring to?

  • Will the City agree that Contractor is responsible for obtaining permits for the Work? Will the City agree that the Contractor is responsible to ensure that the materials furnished or integrated into the Work comply with applicable laws and project specifications?

    Please see Section 8 of the RFQu for the proper procedure for submitting exceptions to Attachment A – Sample Contract.

  • Will the City agree that under Section XVI, where the Consultant will perform Services, and not construction,, that the Contractor is solely responsible to correct any identified defects or its failure to comply with the Contract Documents?

    Please see Section 8 of the RFQu for the proper procedure for submitting exceptions to Attachment A – Sample Contract.

  • Will the City agree that under Section XVI, the Contractor shall be held responsible for its defective work, including the obligation to remove and properly dispose of rejected materials?

    Please see Section 8 of the RFQu for the proper procedure for submitting exceptions to Attachment A – Sample Contract.

  • Will the City agree that under Section XVI, the Contractor shall be responsible to correct any defects in the Work that are discovered during the Warranty period?

    Please see Section 8 of the RFQu for the proper procedure for submitting exceptions to Attachment A – Sample Contract.

  • Will the City agree under Section XVI, that the deductions imposed to correct the Work which did not meet the requirements of the Contract Documents and specs shall be assessed against payments owed to the Contractor?

    Please see Section 8 of the RFQu for the proper procedure for submitting exceptions to Attachment A – Sample Contract.

  • Will the City agree under Section XVIIII, that the Contractor shall be responsible to obtain the permits, licenses and inspections required for the Work?

    Please see Section 8 of the RFQu for the proper procedure for submitting exceptions to Attachment A – Sample Contract.

  • Where termination is such a severe sanction, will the City agree to a minimum of five business days notice to cure the alleged default, breach or noncompliance?

    Please see Section 8 of the RFQu for the proper procedure for submitting exceptions to Attachment A – Sample Contract.

  • Could the city please clarify whether the requested experience for fluid metering facility design and upgrades refers to metering within water/wastewater treatment facilities or within the distribution system?

    Both.

  • Please clarify whether the requirement for “retainage withheld” applies to professional consulting services under this contract. If so, please specify the applicable retainage percentage.

    Please see Section 8 of the RFQu for the proper procedure for submitting exceptions to Attachment A – Sample Contract.

  • RFQu page 22, Section 3.3, Tab 2, Item 1 requires “a minimum of 5 projects and a maximum of 10 projects.” The City's November 12, 2026, response to a question regarding subconsultant experience confirms that subconsultant projects should be included. Question: Will projects performed by subconsultants be evaluated and scored equally to those performed by the prime consultant, or will the prime consultant's experience receive greater consideration?

    The proposer should submit as a team with their key subconsultants included. The subconsultant projects will be judged equally. The ratio of prime to subconsultant projects highlighted is left in the purview of the proposing team.

  • RFQu pages 22–23, Section 3.2.5, Tabs 1 and 2, establish specific content requirements and page limits for firm qualifications, personnel experience, and subconsultant management. Question: Would the City allow an additional section to introduce each proposed subconsultant, including its firm background, role on the team, and relevant experience? We believe this information would benefit the City by providing a clearer understanding of each subconsultant's qualifications, the specialized expertise they bring, and why they were specifically selected to complement the prime consultant's capabilities. Would the City permit a separate section of up to one page per subconsultant, in addition to the prescribed content and page limits, to provide this information?

    Please see Addendum #2.

  • RFQu page 21, Section 3.2.4, states: “Upload the proposal including all required information, completed forms, and supporting documentation in the appropriate tabs onto OpenGov by the due date and time.” RFQu page 24, Section 3.3, states: “All required Additional Proposal Mandatory Forms must be completed and included with the submitted proposal.” However, Section 10, Vendor Submission Requirements and Attestations, provides separate OpenGov upload fields for the required forms and supporting documents. Question: Please clarify whether the required forms and supporting documents must be included within the proposal PDF in addition to being uploaded separately in their designated OpenGov fields, or whether uploading them separately is sufficient to satisfy the RFQu requirements.

    Please do both.

  • Can the conflict of interest provision in Section 24 be limited to direct, actual conflicts arising from the Engineer's services for another client that materially interfere with the engineering team’s ability to perform the services required for the respective City project, rather than applying generally to other clients or projects within the Treasure Coast area? Additionally, if such a conflict arises and cannot otherwise be reasonably resolved, can the City agree to terminate the services on the specific project giving rise to the conflict, rather than requiring the Engineer to terminate its relationship with the other client?

    Please see Section 8 of the RFQu for the proper procedure for submitting exceptions to Attachment A – Sample Contract.

  • Can the prime use subconsultants for disciplines like electrical/I&C/SCADA, structural, geotechnical, survey and landscape architecture? Should those subconsultants be named in the submittal, if so will their projects count towards the total number of projects?

    The proposer should submit as a team with their key subconsultants included. The subconsultant projects will be judged equally. The ratio of prime to subconsultant projects highlighted is left in the purview of the proposing team.

  • Two versions of Attachment A were posted with different Section IX indemnification language. One says “indemnify, defend, and hold harmless… against any and all claims.” The other matches RFQu Section 4.1, “to the extent caused by” the consultant’s negligence. Please confirm which version governs. Please also confirm that indemnification for professional services will be limited as Section 725.08, F.S. requires.

    An updated version of the Sample Contract has been uploaded and included in Addendum No. 1. The updated contract contains the same indemnification language as Section 4.1 of the RFQu and shall govern. Indemnification obligations related to professional services are limited to the extent permitted and required by Section 725.08, Florida Statutes.

  • Please clarify how the requirement to provide five (5) to ten (10) representative projects applies to a team consisting of a prime consultant and subconsultants. Should the five (5) to ten (10) projects represent the combined experience of the entire proposed team, or is each firm expected to submit its own set of representative projects?

    The proposer should submit as a team with their key subconsultants included. The subconsultant projects will be judged equally. The ratio of prime to subconsultant projects highlighted is left in the purview of the proposing team.

Plain text

OpenGov categories

  • 91842 · Engineering Consulting