Description

These proposed improvements will address the capacity and operational deficiencies under the existing conditions for the area shown in Exhibit A . The sewer systems were constructed with 6” minimum diameter instead of the City’s current minimum standard 8-inches in diameter. This old 6-inch pipe is experiencing significant maintenance problems such as offset joints and root intrusion and its improvement is a priority for the City. Implementation of this program will improve the overall performance, reduce maintenance costs, ensure capacity for future developments, and maintain the reliability of the sewer system. The City of Anaheim Public Works Operations team has identified a previously unknown sag or siphon between manholes SW070319 and SW071102 in La Palma Ave. This segment has caused operational issues. This project will identify solutions to remove this operational deficiency. City survey shows the 21-inch sewer line on the south side of La Palma at a lower elevation than the 10-inch sewer line. Additionally, this project aims to remove the existing siphon from SW070314 to SW071101 in the intersection of La Palma and Harbor. The identification of any feasible solutions to this removal is requested in the projects Preliminary Design Report (PDR). Project Details Important Instructions for Electronic Submittals The City of Anaheim is accepting electronic bid submissions. Bidders shall create a FREE account with OpenGov Procurement by signing up at https://procurement.opengov.com/signup . Once you have completed account registration, browse back to this page, click on "Draft Response", and follow the instructions to submit the electronic bid. Scope of Work or Project Details Please see the Attachments section for specifications and attachments. Introduction Summary These proposed improvements will address the capacity and operational deficiencies under the existing conditions for the area shown in Exhibit A . The sewer systems were constructed with 6” minimum diameter instead of the City’s current minimum standard 8-inches in diameter. This old 6-inch pipe is experiencing significant maintenance problems such as offset joints and root intrusion and its improvement is a priority for the City. Implementation of this program will improve the overall performance, reduce maintenance costs, ensure capacity for future developments, and maintain the reliability of the sewer system. The City of Anaheim Public Works Operations team has identified a previously unknown sag or siphon between manholes SW070319 and SW071102 in La Palma Ave. This segment has caused operational issues. This project will identify solutions to remove this operational deficiency. City survey shows the 21-inch sewer line on the south side of La Palma at a lower elevation than the 10-inch sewer line. Additionally, this project aims to remove the existing siphon from SW070314 to SW071101 in the intersection of La Palma and Harbor. The identification of any feasible solutions to this removal is requested in the projects Preliminary Design Report (PDR). Timeline Release Project Date: October 29, 2026 Question Submission Deadline: November 19, 2026, 2:00pm Response Submission Deadline: December 3, 2026, 2:00pm Project Contact Joshua Vargas Associate Engineer 200 S Anaheim Blvd Anaheim , CA 92805 Email: jovargas@anaheim.net Phone: (714) 765-5100 Ext: 5835 Evaluation Phases Vendor Questionnaire Attachments

Published attachments
Public questions and answers
  • What is the Project Duration?

    Item 19 under Section V General Project Requirements and Scope of work states the project should be ready for public bidding 12 months after the Notice to Proceed is issued.

  • What is the Engineer's Estimate?

    There is no engineers estimate. This RFP is for Design Services.

  • Section 1 & 2 request Ready-mix subs name. Is this a typo or is it needed? Thanks

    If there are no ready mix subcontractors to be listed on the Designation of Subcontractors form, then it is not needed.

  • Does the 12-inch Sewer C-8, No. 315 and 8-inch Sewer Plan No. 5080 still exist?

    City Operations and survey can confirm existing facilities in the field with the selected consultant.

  • In the 25-28_MHDips.pdf, several of MHs have Point numbers but without the MH ID No., and several of the MH ID photos are inconsistent with the GIS lay-out, such as ID #071103.

    There may be some inconsistencies with the topo and MH Dips exhibit. City survey can work with the selected consultant to get the proper information and data.

  • Please provide additional MH ID photos’ information to cover the entire project site.

    City survey can work with the selected consultant to get any requested data.

  • Please provide the existing 8-inch and 12-inch & 10-inch sewer plans along La Palma Avenue.

    As-builts can be found under the supporting attachments - A - La Palma SSIP As-Builts. Existing as-builts can also be found here. https://www.anaheim.net/2329/Public-Works-Records

  • Please provide all the existing 6-inch alley sewers’ plans and the 10-inch-north & 6-inch-south sewers in Harbor Blvd.

    As-builts can be found under the supporting attachments - A - La Palma SSIP As-Builts. Existing as-builts can also be found here. https://www.anaheim.net/2329/Public-Works-Records

Plain text

OpenGov categories

  • 30500 · Engineering And Architectural Equipment, Surveying Equipment, Drawing Instruments, And Supplies
  • 89063 · Sewer Analyzing, Monitoring, Probe and Related Equipment
  • 91063 · Public Utilities: Water, Sewer and Gas Maintenance and Repair
  • 91842 · Engineering Consulting
  • 91894 · Traffic Consulting
  • 92500 · Engineering Services, Professional
  • 92517 · Civil Engineering
  • 92533 · Engineer Services, Professional
  • 92535 · Environmental Engineering
  • 92536 · Engineering Services (Not Otherwise Classified)
  • 92546 · Geotechnical Engineering
  • 92587 · Sewage Collection, Treatment, and Disposal/Engineering