Lower Spring Branch Stormwater Improvements
Description
Project consist of stormwater improvements to provide flood reduction with the replacement of bridges on Springtime Avenue and Overbrook Avenue and a double concrete box culvert on Douglas Avenue. The Contractor shall provide copies of a Current License/Registration with the state of Florida and Pinellas County (if applicable) in the bid response. The Contractor shall provide fixed project signs as described in Section III, Section 23 of the Contract Documents. The final number of project signs will be determined at the beginning of the project based on the Contractor's schedule of work submitted for approval. Additional project signs may be required at no additional cost to the city due to the Contractor's schedule of work. Contract Period: 548 Consecutive Calendar Days Lower Spring Branch Stormwater Improvements-Douglas Avenue Mobilization Work Zone, Traffic Control Sediment Barrier Floating Turbidity Barrier Clearing and Grubbing (Includes removal of guardrail, handrail, pavement, etc.) Removal of Existing Structures (Box Culverts, Endwalls, and Inlet Structures) Removal of Existing Concrete Regular Excavation Embankment Concrete Class IV, (Double 12' X 9' RCBC, Wingwalls, and Headwalls) Reinforcing Steel, Roadway Riprap, Sand-Cement Bags Riprap, Rubble, F&I, Ditch Lining Bedding Stone Utility Fittings, DI/CI F&I Elbow, 6" Ductile Iron Pipe (6" DIP for Potable Water Main Restoration) Utility Fixture, TEAM Valve, Furnish and Install, 6" Utility Fixture, Mechanical Joint Restraint, Furnish and Install, 6" Inlets, Curb, Type P-6, 10' (Pinellas County RC-4) Pipe Culvert, Optional Material, Round 18" S/CD Sheet Piling Steel (For Cofferdam) Subgrade - Type B Stabilization (12", LBR 40) Base - Optional Base (8", Base Group 06, Limerock LBR 100) Asphaltic Concrete (2", Type SP-12.5) Milling of Existing Asphalt Pavement Pipe Handrail - Guiderail, Aluminum Bullet Rail, Double Rail Concrete Curb and Gutter, Type F Shoulder Concrete Barrier Wall, Curb and Gutter Barrier Concrete Sidewalk (6' Width, 4" Thick) Fencing, Wood Fence, 5.1-6.0' Fencing, Vinyl Fence, 5.1-6.0' Fence Gate, Wood, Single, 6.1-12.0' Opening Single Column Ground Sign Assembly, F&I Ground Mount, Less Than 12 SF Thermoplastic, Standard, Yellow, Solid 6" Thermoplastic, Standard, White, Skip 6" Raised Pavement Marker, Type B (Without Final Surface Markings) Object Marker, Type 3 Tree Barricades Root Pruning Lower Spring Branch Stormwater Improvements Contingency- Douglas Avenue This contingency is solely for the pricing table for Douglas Ave. Owners Contingency-10% of the above total for Douglas Avenue Lower Spring Branch Stormwater Improvements-Springtime Avenue Mobilization Work Zone Traffic Control Sediment Barrier Floating Turbidity Barrier Clearing and Grubbing (Includes removal of guardrail, handrail, pavement, etc.) Removal of Existing Structures/Bridges (Bridge Span, Endwalls, and Inlet Structures) Regular Excavation Embankment Concrete Class IV, Substructure (Concrete Cap and Footers) Reinforcing Steel, Roadway Riprap, Rubble, F&I, Ditch Lining Bedding Stone Utility Structure, Below Ground, Adjust/Modify (Includes bypass pumping) Gravity Sewer Pipe (8" DIP for Sanitary Sewer Restoration) Ductile Iron Pipe (6" DIP for Potable Water Main Restoration) Utility Fittings, DI/CI F&I Elbow, 6" Utility Fixture, Mechanical Joint Restraint, Furnish and Install, 6" Utility Fixture, TEAM Valve, Furnish and Install, 6" Sheet Piling Steel (For Cofferdam) Sheet Piling Steel, F&I Permanent Pipe Culvert, Optional Material, Round 18" S/CD Inlets, Curb, Type P-6, 10' (City of Clearwater, Wing Inlet) Conspan Series O326 Bridge 26' X 8.5' Arch (Includes Installation and Headwalls/Wingwalls) Pipe Handrail - Guiderail, Aluminum Fencing, Vinyl Fence, 0.0-5.0' Fencing, Wood Fence, 5.1-6.0' Base - Optional Base (8", Base Group 06, Limerock LBR 100) Subgrade - Type B Stabilization (9", LBR 40) Asphaltic Concrete (2", Type SP-12.5) Concrete Curb and Gutter, Type F Concrete Sidewalk (4' Width, 4" Thick) Milling of Existing Asphalt Pavement American Muscle Docks and Fabrication Lift Ladder (Five step, 4" step width) Traffic Rail Texas Classic - Type T411 Standard (Mod.) Tree Removal Performance Turf, Sod Tree Barricades Root Pruning Tree Mitigation Lower Spring Branch Stormwater Improvements Contingency-Springtime Avenue This contingency is solely for the pricing table for Springtime Ave. Owners Contingency-10% of the above total for Springtime Avenue Lower Spring Branch Stormwater Improvements-Overbrook Avenue Mobilization Work Zone Traffic Control Sediment Barrier Floating Turbidity Barrier Clearing and Grubbing (Includes removal of guardrail, handrail, pavement, etc.) Removal of Existing Structures/Bridges (Bridge Span, Endwalls, and Inlet Structures) Regular Excavation Embankment Concrete Class IV, Substructure (Concrete Footers) Reinforcing Steel, Roadway Riprap, Rubble, F&I, Ditch Lining Bedding Stone Ductile Iron Pipe (6" DIP for Potable Water Main Restoration) Utility Fixture, VAC/AIR Assembly, Furnish and Install, 2" (Air Release Valve) Utility Fittings, DI/CI F&I Elbow, 6" Utility Fixture, Mechanical Joint Restraint, Furnish and Install, 6" Utility Fixture, TEAM Valve, Furnish and Install, 6" Sheet Piling Steel (for Cofferdam) Pipe Culvert, Optional Material, Round 18" S/CD Inlets, Curb, Type P-6, 10' (City of Clearwater, Wing Inlet) Conspan Series O224 Bridge - 24' X 11' Arch (Includes Installation and Headwalls/Wingwalls) Pipe Handrail - Guiderail, Aluminum Concrete Sidewalk (5' Width, 4" Thick) Base - Optional Base (8", Base Group 06, Limerock LBR 100) Subgrade - Type B Stabilization (9", LBR 40) Asphaltic Concrete (2", Type SP-12.5) Concrete Curb and Gutter, Type F Milling of Existing Asphalt Pavement Traffic Rail Texas Classic - Type T411 Standard (Mod.) Tree Removal Performance Turf, Sod Tree Barricades Root Pruning Tree Mitigation Lower Spring Branch Stormwater Improvements Contingency- Overbrook Avenue This contingency is solely for the pricing table for Overbrook Ave. Owners Contingency-10% of the above total for Overbrook Avenue SUPPLEMENTAL TECHNICAL SPECIFICATIONS - Section IVA Supplemental Technical Specifications See Attachment A-Lower Spring Branch Stormwater Improvements-Bid Phase Supplemental Technical Specifications INSTRUCTIONS TO BIDDERS SECTION II INSTRUCTIONS TO BIDDERS 1. COPIES OF BIDDING DOCUMENTS 1.1. Bid Documents, any attachments and addenda are available for download at: https://procurement.opengov.com/portal/myclearwater/projects/304326 . Bidding Documents may include, but are not limited to, plans, specifications, bond forms, contract form, affidavits, bid/proposal form, and addendums. 1.2. Complete sets of Bidding Documents must be used in preparing bids. Neither the City nor the Engineer shall be liable for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents, by Bidders, sub-bidders, or others. 2. QUALIFICATION OF BIDDERS 2. 1 Each prospective Bidder must pre-qualify to demonstrate, to the complete satisfaction of the City of Clearwater, that the Bidder has the necessary facilities, equipment, ability, financial resources and experience to perform the work in a satisfactory manner. An application package for pre-qualification may be obtained by contacting the City of Clearwater, Engineering Division by phone at (727) 562-4750. Pre-qualification requirement information is also available on the City of Clearwater Website at address: www.myclearwater.com/government/city-departments/engineering/construction-management . Contractors wanting to pre-qualify to bid on a project as a General Contractor must do so two weeks (ten workdays) prior to the bid opening date. Bidders currently pre-qualified by the City do not have to make reapplication. It is the Contractor’s responsibility to confirm pre-qualification status before a Bid Opening. The Contractor shall include copies of their current license/registration with the State of Florida and Pinellas County (if applicable) with their bid response. 3. EXAMINATION OF CONTRACT DOCUMENTS AND SITE 3.1.It is the responsibility of each Bidder, before submitting a Bid, to (a) examine the Contract Documents thoroughly; (b) visit the site to become familiar with local conditions that may in any manner affect cost, progress, performance or furnishing of the work; (c) consider and abide by all applicable federal, state and local laws, ordinances, rules and regulations; and (d) study and carefully correlate Bidder's observations with the Contract Documents, and notify Engineer in writing of all conflicts, errors or discrepancies in the Contract Documents. 3.2.For the purposes of bidding or construction, bidder may rely upon the accuracy of the technical data contained in reports of explorations and tests of subsurface conditions at the site which have been utilized by the Engineer in the preparation of the Contract Documents, but not upon non‑technical data, interpretations or opinions contained therein or for the completeness thereof. Drawings relating to physical conditions of existing surface and subsurface conditions (except Underground Facilities) which are at or contiguous to the site and which have been utilized by the Engineer in preparation of the Contract Documents, may be relied upon by Bidder for accuracy of the technical data contained in such drawings but not upon the completeness thereof for the purposes of bidding or construction. 3.3.Information and data reflected in the Contract Documents with respect to Underground Facilities at or contiguous to the site are based upon information and data furnished to the City and Engineer by owners of such Underground Facilities or others, and the City does not assume responsibility for the accuracy or completeness thereof unless expressly provided in the Contract Documents. 3.4.Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders on subsurface conditions, Underground Facilities, other physical conditions, possible conditions, and possible changes in the Contract Documents due to differing conditions appear in the General Conditions. 3.5. Before submitting a Bid, each Bidder shall, at Bidder's own expense, make or obtain any additional examinations, investigations, explorations, tests and studies and obtain any additional information and data which pertain to the physical conditions (surface, subsurface and Underground Facilities) at or contiguous to the site or otherwise which may affect cost, progress, performance or furnishing the work in accordance with the time, price and other terms and conditions of the Contract Documents. 3.6. On request in advance, City will provide each Bidder access to the site to conduct such explorations and tests at Bidder's own expense as each Bidder deems necessary for submission of a Bid. Bidder shall fill all holes and clean up and restore the site to its former condition upon completion of such explorations and tests. 3.7. The lands upon which the Work is to be performed, rights-of-way and easements for access thereto and other lands designated for use by the Contractor in performing the Work are identified in the Contract Documents. All additional lands and access thereto required for temporary construction facilities or storage of materials and equipment are to be provided by the Contractor. Easements for permanent structures or permanent changes in existing structures are to be obtained and paid for by the City unless otherwise provided in the Contract Documents. 3.8. The submission of a Bid will constitute an unequivocal representation by the Bidder that the Bidder has complied with every requirement of these Instructions to Bidders and that, without exception, the Bid is premised upon performing and furnishing the Work required by the Contract Documents by such means, methods, techniques, sequences or procedures of construction as may be indicated in or required by the Contract Documents, and that the Contract Documents are sufficient in scope and detail to indicate and convey understanding of all terms and conditions of performance and furnishing of the work. 4. INTERPRETATIONS AND ADDENDA 4.1. All questions as to the meaning or intent of the Contract Documents are to be directed in writing to the Engineer. Interpretations or clar GENERAL CONDITIONS Section III - General Conditions can be found on the City's website at: https://www.myclearwater.com/Business-Development/Doing-Business-with-the-City/Engineering-Construction-Bid-Information/Contract-Specifications TECHNICAL SPECIFICATIONS SCOPE OF WORK Project Name: Lower Spring Branch Stormwater Improvements Project Number: 14-0048-EN Scope of Work: Project consist of stormwater improvements to provide flood reduction with the replacement of bridges on Springtime Avenue and Overbrook Avenue and a double concrete box culvert on Douglas Avenue. The Contractor shall provide copies of a Current License/Registration with the state of Florida and Pinellas County (if applicable) in the bid response. The Contractor shall provide fixed project signs as described in Section III, Section 23 of the Contract Documents. The final number of project signs will be determined at the beginning of the project based on the Contractor's schedule of work submitted for approval. Additional project signs may be required at no additional cost to the city due to the Contractor's schedule of work. Contract Period: 548 Consecutive Calendar Days Section IV - Technical Specifications Section IV - Technical Specifications can be found on the City's website at: https://www.myclearwater.com/Business-Development/Doing-Business-with-the-City/Engineering-Construction-Bid-Information/Contract-Specifications Section V - Contract Documents Section V - Contract Documents can be found on the City's website at: https://www.myclearwater.com/Business-Development/Doing-Business-with-the-City/Engineering-Construction-Bid-Information/Contract-Specifications PRICING SHEET It is the City of Clearwater's intent to award one bidder for all three locations. SUBMITTAL REQUIREMENTS
Published attachments
- Lower Spring Branch Stormwater Improvements - Bid Phase Supplemental Technical Specifications - Addendum
- Lower Spring Branch Stormwater Improvements - Bid Plan Set - Addendum
- 20260918_REVERIFICATION LETTER SAJ-2021-01322
- Lower Spring Branch Stormwater Improvements 100% Design_FTR_RGB_10-23-26
- FTR UWS - Lower Spring Branch.docx
- Lower_Spring_Branch_Stormwater_Improvements_(Addendum_#2_Revision).pdf
Addenda and notices
Official Notice #1: Pre Bid Agenda · 1
Addendum #1 · 1
Please use the See What Changed link to view all the changes made by this addendum.
Official Notice #2: Pre-Bid Sign in Sheet · 2
Addendum #2 · 2
Updated pricing table, documents in attachments. Please review the questions and answers. Please use the See What Changed link to view all the changes made by this addendum.
Public questions and answers
1. At Springtime Avenue, the house property adjacent to the creek ( immediately south of the bridge) has signs on the site that indicate “City of Clearwater”. Please ownership status status of this property, and if it is available to access the work site through this property. 2. Plan Sheet 49 shows concrete to the bottom of 6-foot embedment for the Soldier Pile Wall. This will be 6-feet below the Creek bottom and it will be very expensive to pour concrete that far below the ground and adjacent to/in the Creek bottom. a. Our Sub advises that this Concrete detail is often seen with *wood* timbers. b. Since these are Plastic Timbers, contractor does not see the application here. c. If Concrete at bottom is deleted , would Engineer need another couple of feet of Timber Piling driven ? 3. Dock Sub proposes to drive these plastic Timbers. Please confirm that these Piles will not be required to be Drilled into place instead. 4. Plan Sheet 49 shows the Soldier Pile Wall to be constructed next to homeowner’s hardscape improvements behind 1839 Springtime Avenue . Please clarify Contractor’s equipment access to this work area . 5. How will damage to these existing features at 1839 Springtime Avenue be paid ? 6. Plan Sheet 49 shows a ‘Lift Ladder’ at the Sheetpile Retaining Wall, on the *north side of bridge. Is this ‘Lift Ladder’ also needed at the Soldier Pile Wall on the *south side of the bridge, which replaces the old Dock at 1839 Springtime Ave? If so, that would make the Bid Quan
1. The properties located at 1838 Springtime Avenue and 1843 Springtime Avenue are owned by the City of Clearwater. The existing structure at 1843 Springtime Avenue is scheduled for demolition by others prior to execution of the construction contract. Contractors may propose use of these City-owned properties for construction access, staging, and related activities, subject to review and prior written approval by the City. 2. The soldier pile wall referenced on Plan Sheet 49 is being removed from the project scope by addendum. Refer to the forthcoming addendum for revised plans and specifications. 3. The soldier pile wall referenced on Plan Sheet 49 is being removed from the project scope by addendum. Refer to the forthcoming addendum for revised plans and specifications. 4. The soldier pile wall referenced on Plan Sheet 49 is being removed from the project scope by addendum. Refer to the forthcoming addendum for revised plans and specifications. 5. The scope of work associated with the existing improvements at 1839 Springtime Avenue is being revised by addendum. Work at this property will be limited to that necessary for construction of the proposed wing walls, as shown in the revised Contract Documents. The Contractor shall be responsible for protecting existing improvements and restoring any damage resulting from construction activities. 6. The soldier pile wall on the south side of the bridge is being removed from the project scope by addendum. Only one (1) lift ladder is
1. Is it the intent of this project for all three locations to be awarded?
Yes.
1. Will all three locations be allowed to be performed immediately after each other?
Yes. Traffic Control Plans (TCP) in the plan set were designed to accommodate one crossing at a time being closed. Contractor to submit a TCP to appropriate entity for approval prior to construction activities.
3. Can the three locations be worked on simultaneously?
Yes. Traffic Control Plans (TCP) in the plan set were designed to accommodate one crossing at a time being closed. Contractor to submit a TCP to appropriate entity for approval prior to construction activities.
4. Is a pre and post topo survey required for each location to verify excavation and embankment quantities, or will this be measured by the truck ticket?
Refer to Pinellas County Technical Specifications in the Supplemental Technical Specifications for the Douglas Avenue project area. Survey not required for Springtime Avenue and Overbrook Avenue. Refer to City of Clearwater Technical Specifications.
5. Please confirm which project locations will be built per City of Clearwater specifications or Pinellas County specifications?
Pinellas County specifications are only applicable for the Douglas Avenue site, as referenced in the Technical Specifications and Bid Form.
6. Please confirm that an office is not required as part of this project.
Structure at 1838 Springtime Avenue to be used as potential construction field office (Contractor would be responsible for securing Temporary Use Permit with the City of Clearwater prior to use of building).
7. Is builders risk required for this project?
Builder's Risk is not required for this project.
8. If builders risk is required for this project, please confirm if flood / wind coverage is required?
Builder's Risk is not required for this project.
9. Does the city have any potential laydown yards nearby?
City of Clearwater owned property at 1843 Springtime Avenue and Overbrook Park are potential staging areas for construction.
11. Please confirm the homeowner is aware of the plan to remove there concrete dock along springtime ave? a. Can plans / permits for this docks construction be provided?
See Addendums
12. Can the properties at 1838 and 1843 Springtime Ave be used as laydown yards / storage areas since they are now owned by the City of clearwater?
City of Clearwater owned property at 1843 Springtime Avenue and Overbrook Park are potential staging areas for construction.
13. Will seed and mulch be acceptable restoration of 1838 and 1843 Springtime ave. if used as storage yards?
Refer to requirements specified in the Paving, Grading, and Drainage Notes section of the General Notes sheet (Sheet #3) of the plan set.
14. Will the existing buildings / structures be cleared at 1838 and 1843 Springtime Ave. prior to construction commencing?
Structures at 1843 Springtime Avenue are scheduled to be demolished (by others) prior to construction. Structure at 1838 Springtime Avenue to be used as potential construction field office (Contractor would be responsible for securing Temporary Use Permit with the City of Clearwater prior to use of building).
15. Please confirm that unsuitable material removal and replacement, if encountered will be paid for out of the projects contingency funds?
Yes.
16. Can flow information be provided for spring branch?
Channel flows range from 450 CFS (Mean Annual) and 1000 CFS.
17. Will the water / reclaim forcemains be able to be shut down during construction, or will temporary mains need to be installed to facilitate construction?
No impacts/adjustments to the existing reclaimed water main are anticipated. Potable water mains are to remain active during construction. Refer to plans for notes and adjustments to the potable water mains.
18. For the gravity sewer along springtime Ave. a. Please provide flowrates of this sanitary system, and flow direction. b. Please provide a GIS map of the sanitary sewer at this location. c. Is it the Cities intent to bypass this sanitary line until bridge construction is completed?
The sanitary sewer flow rate for this section is estimated to be roughly 375 GPM, at maximum condition. The flow direction is south. Flow is to be bypassed until installation of new sanitary sewer pipe is complete.
19. Does BABA requirements apply to this project?
BABA requirements do not apply to this project.
20. Is domestic material a requirement for this project?
Domestic material is not a specific requirement for this project.
21. The plans call for a septic tank permit and a building permit to be pulled. Please clarify why these permits are needed for culvert / bridge work?
General note is not applicable to this project.
22. What cost should the contractor anticipate for the Pinellas county ROW permit, or is this cost already covered?
Contractor is responsible for obtaining ROW permit from Pinellas County.
23. Per note 22 on plan sheet 3 the existing balustrade is to be salvaged. a. Is the entire balustrade to be removed or just the end section? b. Can plans or details for this balustrade be provided? c. Is the contractor liable if the existing concrete structure does not hold together during removal?
Existing ballustrade can be removed in sections, if required. If removed in sections, contractor would be responsible for reassembling the ballustrade to existing conditions. Contractor to coordinate removal efforts with the City of Clearwater.
24. Please confirm that only the plaques are to be salvaged on springtime ave and not the wall sections.
Only the plaques are to be salvaged at the Springtime Avenue location.
25. Please confirm that cctv and cleaning of existing storm lines are not required. If so, please provide a pay item to cover the costs.
Not required for existing storm on this project.
26. Please provide the UWS sheets for the utility owners within the project locations, clearwater gas and frontier in particular appear to need UWS sheets, as well as Duke energy if they are in conflict.
Utility adjustments are shown in the plans (Sheets 26-28). Utility Work Schedules from utility owners will be provided.
27. Is the existing curb removal covered in the concrete removal pay item, or is it incidental to the curb replacement?
Existing curb removal is to be included in Pay Item 110 - Clearing and Grubbing.
28. Are any project signs required, and if so is one needed per project site?
Project signs are required as referenced in Section III - 23.8 Typical Project Sign of the Technical Specifications.
29. Will VMB’s be required continuously throughout the project, or only 14 days in advance of the proposed road closures?
VMBs are to be placed 14 days in advance of any road closure. Road closure/detour signage shown in Traffic Control Plans is to be set for the duration of construction activities.
30. Please provide the existing plans for headwall, wing wall, box culvert, and bridge crossings so the appropriate cost can be figured for removals.
Existing As-Builts for these sites are unavailable. Existing conditions are shown in the plan set.
31. Temporary construction access will be needed on the NE side of Douglas Ave. to facilitate the coffer dam required to remove and install the new box culvert.
Contractor to coordinate access with Pinellas County.
32. Temporary construction access will be needed on the NW and SW side of Overbrook Ave. to facilitate the coffer dam required to remove and install the new box culvert.
Contractor to coordinate access with the City of Clearwater.
33. Please confirm that the proposed box culvert can be pre-cast?
Proposed box culvert can be pre-cast.
34. Please confirm the anticipated start date of this project?
January/February 2027.
35. There are temporary sheet pile walls shown for overbrook and springtime ave. a. How is the contractor paid for these temporary sheets? b. What is the intended toe and top elevations for these sheets? c. What is the intent of these sheets? It appears they are being used on the four corners to support the adjacent properties from washout, while the boxes around the foundations will need to be a tight sheeting pit to pour the foundations. d. Are the pits around the foundation required, or will the contractor be able to cofferdam off the upstream and downstream ends of each crossing location? e. Why is there no temporary sheeting shown for Douglas Ave?
Items a & b: Per 455-12.6.2, when the temporary steel sheet pile walls are not detailed in the Plans, the cost of furnishing and installation shall be incidental to cost of other related items, and no separate payment shall be made. Item c, their intent depict possible limits of excavation. As these walls are not temporary critical, the Contractor may use other means and methods of soil retention. Item d - the Contractor may use other methods to prevent water intrusion. Item e - The contractor may choose temporary sheeting.
36. Can trees 1, 2, 3, 12, 15, and 16 be removed on Douglas Ave? They are in conflict with the proposed construction / access to the construction. Additionally, their barricades take up the entire easement on this side of the bridge.
Additional trees on private property cannot be removed. Invasive trees can be removed, if needed. Contractor must get City approval for any additional tree removals that are not specified in the plan set. If additional removals are approved, there will be no additional payment to the Contractor by the City. Contractor would be responsible for mitigation per City criteria at no additional cost to the City.
37. Can tree 30 be removed on Springtime Ave? It is in conflict with the proposed construction / access to the construction.
Additional trees on private property cannot be removed. Invasive trees can be removed, if needed. Contractor must get City approval for any additional tree removals that are not specified in the plan set. If additional removals are approved, there will be no additional payment to the Contractor by the City. Contractor would be responsible for mitigation per City criteria at no additional cost to the City.
38. Can trees 35, 38, 41, 47, 48, 51, and 54 be removed on Overbrook Ave? They are in conflict with the proposed construction / access to the construction.
Additional trees on private property cannot be removed. Invasive trees can be removed, if needed. Contractor must get City approval for any additional tree removals that are not specified in the plan set. If additional removals are approved, there will be no additional payment to the Contractor by the City. Contractor would be responsible for mitigation per City criteria at no additional cost to the City.
39. All three projects have a special LS tree Mitigation pay item. Please provide clarification on what this is for, and what costs need to be included.
Pay Item is for tree mitigation, as referenced in the Tree Disposition Table on Sheet 13 of the plan set.
40. Please consider changing the tree mitigation pay items to an allowance pay item with a City provided cost.
Refer to disposition tables of the plan set and bid form.
41. Please provide a tree mitigation cost schedule so the contractor knows what the costs are per each type/size tree removed.
Refer to disposition tables of the plan set and bid form.
42. Please confirm that the existing gas lines are not in conflict with the proposed permanent and temporary sheeting required for these projects.
Existing gas mains are to be abandoned prior to construction and removed, as needed for construction, by the contractor. Clearwater Gas is to install new gas mains after construction is complete.
43. Where is pay item 455 Sheet piling steel temp- critical for 1,000 SF at on the Douglas Ave. Project? a. Is the contractor correct to assume this is our coffer dam for the install of the box culvert? b. Can this be shown on the plans like the other two locations?
Pay Item 455 is listed in the Stormwater section of the Bid Form and to be used as a cofferdam, where needed.
44. Please confirm if the mechanical joint restraint pay item is for restraining the existing watermain, or if it is for the proposed watermain.
The mechanical restrained joint quantity specified in the Bid Form is the anticipated required amount of joints to connect the proposed main to the existing main, per City details and specifications.
45. Can the question deadline and bid due date be extended for this project?
No extension is anticipated.
46. Please confirm that 6” of limerock roadbase is acceptable in lieu of 12” stabilization per FDOT indexes.
Permitted, but must meet City of Clearwater and FDOT criteria. No additional cost to be paid by City to Contractor.
What is the engineer's estimate?
Engineer's Estimate is not provided.
Will the Owner consider an Alternate Design/ brand for the Conspan bridges before bid date?
Alternate design/brands may be considered provided the culvert opening meet hydraulic requirements.
Does the existing water main piping need to be restrained back from the new valves we are installing? Or do we assume the existing water main is fully restrained?
The mechanical restrained joint quantity specified in the Bid Form is the anticipated required amount of joints to connect the proposed main to the existing main, per City details and specifications.
For the sanitary sewer work, do we assume the existing benches (inverts) will be sufficient, and no reworking of the benches will be required?
Proposed sanitary sewer inverts are to match existing conditions. Contractor is to field verify inverts prior to installation of proposed sanitary sewer pipe.