As of January 2026FedRAMP
Detailed Answer
FedRAMP authorization timelines:
**Agency Authorization Path:**
- Preparation: 3-6 months
- Assessment: 3-4 months
- Authorization: 3-6 months
- Total: 12-18 months
**JAB Authorization Path:**
- FedRAMP Ready: 2-4 months
- Prioritization queue: Variable
- Full assessment: 6-9 months
- Total: 18-24+ months
**Factors Affecting Timeline:**
- Current security posture
- Complexity of cloud service
- Number of security controls
- Availability of 3PAO
- Remediation requirements
**Cost Considerations:**
- Initial authorization: $250K-$750K+
- Annual assessment: $150K-$300K
- Continuous monitoring ongoing